Country: Chile

Contract award: August 2008
Completion: July 2009

Design and construction of one new chimney h=95m
Campiche Power Plant, Chile
Client: Posco E&C

More details...


Country: Chile

Contract award: July 2008
Completion: May 2009

Design and construction of one new chimney h=95m
Angamos Power Plant, Chile
Client: Posco E&C

More details...


Country: Indonesia

Contract award: February 2008
Completion: July 2009

Design and construction of one new chimney h=215m with 2 internal steel liners.
PLTU 1 Jawa Tengah 2x(300-400) MW Coal-Fired Power Plant - Central Java - Indonesia
Client: Zelan-Priamanaya-Tronoh Consortium (ZPT)

More details...


Country: Indonesia


Contract award: Nov. 2007
Completion: September 2009

Design and construction of one new chimney h=215m with 1 internal steel liner.
PLTU 1 Jawa Barat 3x330 MW Power Plant, Indramayu, West Java- Indonesia
Client: China National Electric Equipment Corporation (CNEEC)

More details...


Country: Indonesia


Contract award: Sept. 2007
Completion: July 2009

Design and construction of a new chimney h=210m with 2 internal steel liners.
PLTU 2 Banten-Labuan 2x300 MW Power Plant, West Java- Indonesia
Client: Chengda Engineering Corporation of China (CNEEC)

More details...


Country: Chile


Contract award: July 2007
Completion: Sept. 2008

Design and construction of one new chimney h=95m.
LAS VENTANAS 240 MW Coal Fired Power Plant, Las Ventanas- Chile
Client: Posco E&C

More details...


Country: Vietnam


Contract award: January 2007
Completion: Sept. 2008

Construction of one new chimney h=140m with 2 internal steel liners.
O-Mon Thermal Power Plant, Vietnam
Client: TOA Corporation

More details...


Country: Iran

Contract award: End of 2006
Completion: Sept. 2007

Construction of one new chimney (Incinerator Stack) h=95m with 1 internal steel liner.
South Pars Gas Field Development - Phase 9 & 10
Client: OIEC / GS Consortium

More details...



Country: Italy

Contract award: June 2009
Completion: January 30, 2010

Existing liner dismantling, design, prefabrication and installation of a new liner D=5.30m inside a chimney h=130.00m
ISAB Energy - Priolo, Italy
Client: ISAB Energy

More details...


Country: Italy

Contract award: July 2008
Completion: November 2008

Demolition and re-construction of the whole brick liner of the chimney h=100m (Unit 1 & 2)
Edi Power Plant, S.Filippo del Mela - Sicily, Italy
Client: Edi Power Plant

More details...


Country: Portugal

Contract award: January 2007
Completion: April 2008

Retrofit of one chimney h=224.80m - air pollution reduction equipment project.
Pego Power Plant, Portugal
Client: Alstom S.p.A

More details...


Country: Italy

Contract award: June 2006
Completion: July 2006

Demolition and rebuilding of brick liner sections chimney project.
Raffineria di Gela, Italy
Client: Raffineria di Gela

More details...


Country: Italy

Contract award: June 2006
Completion: July 2006

Demolition and rebuilding of brick liner sections of two chimneys.
ERG Refinery, Italy
Client: Erg S.p.A

More details...


Country:Kingdom of Saudi Arabia (KSA)

Contract award: Nov.2006
Completion: October 2009

Refurbishment works of n.2 chimneys h=150m.
Jeddah Power Plant Stage IV - FGD Project
Client: Saudi Archirodon Ltd.

More details...



Country: Kingdom of Saudi Arabia (KSA)

Contract award: Nov. 2006
Completion: May 2007

Engineering, procurement, and installation of refractory lining for 8 catofin reactors.
APPC PDH PP Project - Al Jubail
Client: Samsung

More details...


Country: Kingdom of Saudi Arabia (KSA)

Contract award: Sept. 2006

Refractory lining of n. 7 cracking furnaces at Tasnee Ethylene Plant - KSA
Client: Linaco (Linde)

More details...


Country: Bahrain / KSA

Contract award: June 2006
Completion: April 2007

Refractory lining of n.8 ethylene cracking furnaces (convections)
Sharq 3rd Expansion Project
Client: TCI (convections) & Al Rushaid Co. (radiant)

More details...


 

 


 

Country: Italy

Contract award: October 2009
Completion: November 2009

Refractory maintenance of FCCU Plant of Raffineria di Milazzo in Milazzo, during the autumn 2009 turn-around.
Client: Raffineria di Milazzo


 

Country: Italy

Contract award: May 2009
Completion: July 2009

Refractory maintenance of FCCU Plant of SARAS Refinery in Sarroch, during the spring turn-around.
Client: Saras


 

Country: Italy

Contract award: January 2009
Completion: February 2009

Refractory maintenance of FCCU Plant of ERG Refinery in Priolo, during the winter turn-around.
Client: ERG


Country: Italy

Contract award: March 2009
Completion: April 2009

Refractory maintenance of FCCU Plant of Esso Refinery in Augusta during the spring turn-around.
Client: ESSO


Country: Italy

Contract award: October 2008
Completion: November 2008

Refractory maintenance of FCCU Plant of SARPOM Refinery in Trecate during the autumn 2008 turn-around.
Client: SARPOM / SICES


Country: Italy

Contract award: April 2008
Completion: May 2008

Refractory maintenance of MHC2 Plant of Saras Refinery in Sarroch during the spring 2008 turn-around.
Client: Saras


 

Country: Italy

Contract award: April 2008
Completion: May 2008

Refractory maintenance of Lube and Fuels Plants at Esso Refinery in Augusta during the spring 2008 turn-around.
Client: ESSO


 

Country: Italy

Contract award: Sept. 2007
Completion: November 2007

Refractory maintenance of various plants at Esso Refinery in Augusta during the autumn 2007 turn-around.
Client: ESSO


Country: Italy

Contract award: April 2007
Completion: May 2007

Refractory maintenance of gassifier reactors at ISAB Energy Plant in Priolo
Client: ERG - ISAB Energy

More details...


 

Country: Italy

Contract award: May 2007
Completion: June 2007

Refractory maintenance during the 2007 turn-around at the Raffineria di Roma. The following plants were repaired:

- Platforming
- Heaters combustion
- Chambers sulphur
- Recovery units
Client: Demont - Sina Service

Chimney inspection with video camera

Description Project Title Client Location/Country
Design, Procurement, and Construction of n.2 chimneys h=120m with Pennguard System (borosilicate), directly applied on the windshield inner surface ROVINARI - Turn-Key WFGD Units 3-4-5-6
CHIMNEY H. 120 m
Alstom Power Italia S.p.A Rovinari - Romania
Design, and Construction of n.1 chinmey h=150m with 3 liners protected by vinylester SHOAIBA STAGE III Saudi Archirodon Ltd. Shoaiba - KSA
Design, prefabrication and installation of new FRP liner D=4.20m inside a chimney h=60.50m
VENTANAS 2 POWER PLANT Alstom Brasil Energia e Transporte Ltda Las Ventanas - Chile
Design, Procurement, and Construction of n.1 chimney h=240m with 2 liners protected by Pennguard System (borosilicate) TANJUNG JATI "B" 2x660MW COAL FIRED POWER PLANT
CHIMNEY H.240.00 m -
No. 2 FLUES D.6580
Mitsui & Shipbuilding Co. Tanjung Jati - Indonesia
Design, Procurement, and Construction of n.1 chimney h=220m with 2 liners protected by vinylester PAITON EXPANSION PROJECT
815MW Coal Fired Power Plant
TOA Corporation Paiton - Indonesia